Georgetown, Guyana – More than 50 derelict vehicles have been removed from North Georgetown as the Government advances its road shoulder improvement programme, with another 58 vehicles identified for removal.
The initiative, being led by the Ministry of Public Works, aims to improve parking facilities, strengthen roadside drainage and enhance road safety while making better use of public spaces across the capital.
Minister of Public Works Bishop Juan Edghill conducted a walkthrough on Thursday, November 12, inspecting completed sections of the project, including the area outside The Bishop’s High School on Carmichael Street.
Improved Parking and Safer Roads
During the inspection, Minister Edghill highlighted the benefits of the upgraded road shoulders, particularly in areas surrounding schools where motorists previously had limited space to stop and pick up or drop off students.
The improved section outside The Bishop’s High School has created additional parking space, reducing the need for vehicles to stop directly along the roadway.
The Minister noted that the changes are expected to improve traffic movement and provide safer conditions for the hundreds of children who use the area daily.
He also explained that clearing abandoned vehicles and other roadside obstructions would help reclaim public spaces and make roads more accessible for residents and businesses.
Existing Trees and Greenery to Be Preserved
Addressing concerns about the removal of grass and changes to the appearance of roadside verges, Edghill assured residents that existing trees will remain and that greenery will return once the work is completed.
He explained that the construction process involves removing muddy surfaces and replacing them with compacted layers of sand, crusher run and sand screening.
The specially prepared surface is designed to provide a stronger foundation for vehicles while allowing water to penetrate the ground and reach the underlying water table, supporting surrounding trees and vegetation.
The Ministry also plans to introduce additional ornamental plants as part of efforts to improve the appearance of Georgetown’s streets.
Ministry Addresses Residents’ Concerns
The Minister acknowledged complaints about the way some contractors initially carried out the works, including dumping construction materials along roadways and excavating extended sections before they were ready for filling.
He said the Ministry had intervened to stop these practices and apologised to residents who experienced inconvenience.
Edghill also pointed to protective barriers installed around trees, including a large tree along Middle Street, to prevent vehicles from damaging them.
Household Bridges Not Being Altered in Current Phase
The Minister clarified that household bridges and property entrances are not being modified during the current phase of construction.
However, after the road shoulders are completed, the Ministry intends to engage individual households to identify adjustments that may be required to improve water flow. These could include lowering bridge lips or raising bridges where necessary.
He also indicated that contractor supervision would be strengthened and a more aggressive maintenance programme introduced to preserve the quality of completed works.
Government Targets Christmas Completion
The Government is aiming to complete most of the heavy construction activities before Christmas, allowing residents and motorists to benefit from the improved road shoulders.
With more than 50 derelict vehicles already removed and another 58 identified, the programme is expected to continue transforming roadside spaces while improving drainage, parking and safety across Georgetown.