Guyana Power and Light Inc. (GPL) has identified a fault at the Canefield Substation in Region Six and is continuing replacement and repair works aimed at restoring electricity supply to affected customers across Berbice.
Since the disruption began on Thursday, GPL’s management and technical teams have been working around the clock to investigate the problem, conduct troubleshooting and replace faulty components at the facility.
The restoration effort is being led by GPL Deputy Chief Executive Officer of Strategic Operations Bharat Harjohn and Divisional Director of Transmission and Distribution Shaun Hamlet, with technical support from Kalpataru Projects International Limited.
Fault narrowed down to grounding transformer panel
GPL said its technical teams have conducted extensive inspections of the substation’s wiring, electrical panels, busbar and distribution feeders as part of the investigation.
Several defective components were identified during the troubleshooting exercise and have already been replaced.
Following further testing and assessment, the teams narrowed the fault to the grounding transformer panel. Replacement of additional defective components is currently underway.
Testing underway before safe restoration
GPL said further testing of the facility will be conducted after the replacement works are completed to ensure that electricity supply can be safely restored.
The company’s management remains actively involved in the restoration exercise, overseeing the technical teams and coordinating efforts to address the outstanding issues.
GPL explained that the work is being carried out carefully and methodically to ensure all technical problems are resolved before the substation is returned to normal operation.
GPL apologises to affected customers
The utility company acknowledged the frustration, inconvenience and hardship experienced by residents and customers in Berbice due to the prolonged interruption in electricity service.
GPL apologised for the disruption and assured customers that every effort is being made to resolve the fault as safely and quickly as possible.
The company said an estimated restoration time will be communicated in a subsequent update and thanked customers for their patience and understanding while repair works continue.